Kearney Power Project construction is completed

Construction on the Kearney Power Project transmission line is complete, with the new line now energized.

June 12, 2025Updated: June 12, 2025
News Channel NebraskaBy News Channel Nebraska

KEARNEY, Neb.— Construction on the Kearney Power Project transmission line is complete, with the new line now energized.

The Kearney Power Project was first announced at the beginning of November in 2024.

With three and a half years of public involvement, easement acquisitions, and construction, the transmission line was officially energized on June 6. 

The new line will allow increased capacity with the transmission system which will in turn meet the increasing demand, reliability and resiliency of energy service in the Kearney area.

“We appreciate the cooperation of the landowners and the public throughout this entire process,” said Paul Brune, the NPPD Project Manager. “As the Kearney area’s energy needs continue to grow, this project will help ensure reliable energy service to the area for years to come.”

With construction completed, crews are currently working to remove material and equipment from yards and complete property restoration for all affected. 

Information on the Kearney Power Project can be found on nppd.com under the “current projects” tab. 

Regional

Nearly $92 million in federal funding headed to Nebraska communities

Nearly $92 million in federal funding headed to Nebraska communities

South Dakota man dies in crash north of Laurel

South Dakota man dies in crash north of Laurel

Nebraska Rep. Don Bacon joins vote blocking House rule on tariffs

Nebraska Rep. Don Bacon joins vote blocking House rule on tariffs

Federal judge sides with McCook migrant detainee in ACLU Nebraska lawsuit

Federal judge sides with McCook migrant detainee in ACLU Nebraska lawsuit